Skip to content

Renewables Project Canceled as Council Reassesses Wind and Battery Plans

Another big renewables project abandoned, as council changes tune on separate wind and battery plan

A major wind, solar and battery project has been withdrawn from the New England region in northern New South Wales, as another big wind and battery proposal heads to independent review and the local council threatens to change its neutral stance.

TagEnergy, the Portugal-based developer and majority owner of Australia’s biggest wind farm, at Golden Plains in Victoria, has decided to abandon its proposal for the Salisbury Energy Hub after deciding that it no longer stacks up commercially.

Hillview was to combine up to 300 megawatts (MW) of wind capacity, with up to 300 MW of solar and a big battery sized at 1,000 MW and 4,000 MWh. It was to be located near Uralla, and had been developed by Ace Power before being bought by TagEnergy last year.

“TagEnergy has made the difficult decision to discontinue the development of the Hillview Energy Hub,” the company says in a note posted to the project website this week.

“Following a detailed evaluation of the project, including the site’s wind resources and its commercial viability, TagEnergy has determined that the project does not currently meet its investment criteria.

“We would like to thank the landowners, local community, partners and stakeholders for their support and contribution to progressing the project to this stage.”

It is the fourth project to be abandoned in the New England region just in the last five months, amid concern over rising construction costs, transmission bottlenecks and local opposition championed by former deputy prime minister and now One Nation MP Barnaby Joyce.

Origin Energy last month walked away from its proposed 870 MW Skye Ridge wind project near Walcha, Squadron Energy abandoned plans for the 426 MW Boorolong wind project near Armidale in July, while Alinta also dropped its plans for the 900 MW, eight hour Ovens Mountain pumped hydro project.

Another major project, the 700 MW Winterbourne wind farm with a 100 MW, 200 MWh battery, put forward by Danish wind giant Vestas, is facing further scrutiny after being referred to the Independent Planning Commission, which will hold public hearings in December and is seeking further submissions.

Local media reports that the Walcha council is reassessing its “neutral” stance on the project, largely because of concerns that its advice and requests over transport issues have been ignored.

The New England Times reports that Walcha Council resolved to stay neutral on the Winterbourne project at its October 30 meeting, but a motion has now been moved to rescind that stance at its next meeting on December 9, five days before the IPC hearing.

The NE Times says that the neutral stance was a key part of efforts by the previous council to keep a lid on tensions in the community, but the recent departure of one council member, Adam Iuston, has left the council “dominated by anti-renewables campaigners.”

The council says its concerns about roads have been ignored by the NSW Department of Planning, Housing and Infrastructure (DPHI). Their particular concern is about delays on the Thunderbolts Way, which it fears could be double the 10-minute wait time identified in the planning approval.

Road issues have been a major concern for regional councils, with one – Balranald in the south-west of the state – citing the potential threat to its lucrative “grey nomad” trade if caravaners decided to take a detour through less busy highways.

Walcha Council general manager Stephen Parry told the meeting on Wednesday that the referral was made without any consultation with council. “At first glance, it appears that a lot of the improvements in roading that were sought … have not found their way into the draft consent conditions.”

According to the New England Times, deputy mayor Rachel Greig is urging the council to formally object to the development, noting that council had asked for a bond, roads repaired to a set standard, and turbines removed from within 10 kilometres of town, and none of it had been granted.

“Council decided to be neutral before they even looked at the EIS, so council didn’t actually look at the project before they decided to be neutral,” Deputy Mayor Greig said, according to the New England Times.

“They haven’t changed a single thing, so it’s time for council to actually object. It’s time for council now to say actually there is way too much risk.”

Currently, only one wind farm is actually being built in NSW, at Uungula in the central west, despite the threat of imminent closure of more of its ageing coal fired power stations.

To support independent media, and help combat the spread of deliberate misinformation and disinformation about the energy transition, you can click here to make a one off donation or become a regular supporter of Renew Economy.

To join more than 29,000 others and get the latest clean energy news delivered straight to your inbox, for free, click here to subscribe to our free daily newsletter.

Giles Parkinson

Giles Parkinson is founder and editor-in-chief of Renew Economy, and founder and editor of its EV-focused sister site The Driven. He is the co-host of the weekly Energy Insiders Podcast. Giles has been a journalist for more than 40 years and is a former deputy editor of the Australian Financial Review. You can find him on LinkedIn and on Twitter.

Share this:
Facebook
X
LinkedIn
Reddit
Email
Print