LONGi will supply 176 megawatts (MW) of its Hi-MO 9 solar modules to help convert the rehabilitated Muswellbrook coal mine into a solar–battery hybrid project.
Alongside 176MW DC of solar capacity, the project will feature a 100MWh battery energy storage system, occupying approximately 482 hectares of rehabilitated mining land.
Developed by OX2, the project is under construction, with full commissioning and grid connection expected in 2028. LONGi will supply approximately 300,000 of its Hi-MO 9 photovoltaic modules, representing 135MW AC of generation capacity.
The modules incorporate LONGi’s HPBC 2.0 back-contact technology, designed to improve energy conversion efficiency and performance in challenging environmental conditions.
Subscribe to the Energy newsletter and discover all you need to know about the energy transition.
Don’t miss a second and subscribe to Energy in print.
The technology achieves module efficiencies of up to 24.8 per cent, with a temperature coefficient of -0.26 per cent per degree Celsius – built to brave Australia’s intense summer heat.
LONGi president of utility – Europe Leon Zhang said the project underlined what can be achieved by repurposing former mining sites.
“The Muswellbrook solar farm is a prime example of sustainable land rehabilitation,” Zhang said. “Supplying our flagship Hi-MO 9 modules to this project proves the market’s deep trust in LONGi’s technological leadership, and product reliability.”
The solar farm is expected to generate approximately 347 gigawatt-hours of electricity annually.
Construction, which began in May 2026, is being delivered by a joint venture between Bouygues Construction Australia and Equans Solar & Storage. Up to 200 jobs are expected to be created during peak construction.